Our “Center for Technology in Aviation” development plan covers extensive investments in key infrastructure projects meant to enhance our maintenance and service capabilities.
Our timeline for completion is as follows:
1. Parking Platforms – Ready by mid-2024, providing direct airport access.
2. Service Way – Ready by mid-2024, ensuring seamless airport connectivity.
3. Heavy Maintenance Hangar – Fully operational by the end of 2025.
4. Office & Staff Amenities – Partial completion by the end of 2024, with full functionality by mid-2025, creating a modern and efficient workspace.
5. Component Workshops (expanding beyond current capabilities) – Operational by the end of 2025.
6. Training Center – Operational by mid-2026, offering type rating and recurrent training at our current location.
7. Painting Hangar – Rescheduled for future completion beyond 2026.
8. Engine Test Cell – Also planned for future development.
Together with our partners, we are dedicating resources and expertise to establish a cutting-edge aviation service hub, designed to meet the evolving needs of the industry.